Pipeline Reroute Project
Location
Northern West Virginia
Services
Mapping
Surveying
This project involved the replacement and reroute of approximately 1,500 feet of 14-inch bare steel pipeline with new 12-inch fusion-bonded epoxy (FBE) coated steel pipe. The reroute shifted the pipeline into an area with improved soil stability to enhance long-term integrity and reduce geotechnical risk.
I3 Engineering completed the new pipeline routing, along with the preliminary civil survey and alignment mapping to support design and construction planning. The selected route was developed to avoid unstable ground conditions while maintaining constructability and operational continuity.
The image above shows a portion of the alignment sheet highlighting the area that was avoided as part of the reroute.